Shear Wall Foundation
Construction
October 2007
through
January 2008
Non-Structural
Demolition
April 2007
through
June 2007
Structural Load
Testing
March 2007
Groundbreaking
Ceremony
March 7, 2007
Shear wall
construction and
Column and Beam
Reinforcement
February 2008
through August
2008
First Floor Slab
Construction
September 2008
to Present